Permit Issuance

Permit issuance is dependent on:

  • All reviewing departments must approve your permit submission.
  • All contractor licensing information must be up-to-date.
  • All fees must be paid.
  • Your permit must be paid for and issued within 6 months of the date the application was submitted or it will become expired.

After Issuance

  • You must post a copy of your permit card and the approved permit documents on the jobsite.
  • You may schedule an inspection.
  • You must receive an approved inspection within 6 months of the date permit was issued or your permit will become void.

How to Get Your Permit Card & Approved Plans

The following are options that you have to obtain your approved permit. A physical permit set that includes our approval stamp is required onsite for inspections.

  • You may download your approved plans and print them out yourself.
  • You may have your plans printed at our main office. Printing costs are listed below.
Page Size Cost Per Page
8.5x11 15 cents
11x17 30 cents
Blueprints (36x24) $16 for the first 4 sheets; $4 for each subsequent sheet.